PLEIADES EVENTS
 
04/12/2009 Beginning of the System Technical Qualification Review
19/11/2009 Delivery by Thales Alenia Space of the instrument Flight Model 2 to Astrium
12/11/2009 Delivery by Astrium of the Satellite Flight Model 1 to CNES
September 2009 Rendez-vous between the satellite, the controle center (SDGC) and the mission centres for the complete system tests
February to end of July 2009 The satellite Flight Model 1 successfully passed the environment tests at Intespace: thermal, mechanical, solar generators deploiment and electro-magnetic tests.
January 2009 Rendez-vous between the satellite, the controle center (SDGC) and the mission centres for the complete system tests
End of July 2008 to mid-November 2009 Satellite Assembly Integration and Tests (AIT)
1st half of 2008 Instrument Assembly Integration and Tests (AIT)
November 2007 First programming test of the satellite Flight Model 1. The programming message, generated with the first version newly commissionned of the Programming Chain, was executed on the Satellite Flight Model 1 (in integration at Astrium in Toulouse) and enabled to acquire about 250 images. These images, downloaded using on board equipments representative of the Pleiades X-band station, are being processed on the Imaging Chain, itself newly delivered to CNES.
The success of this test is very promissing and demonstrates a maturity level reassuring while the system tests have not begun yet, over two years before the launch, now schedulled for the beginning of 2010.
July 2007 End of first bus integration.
June 2007 Satellite Critical Design Review.
October 2006 Instrument Critical Design Review.
June 2006 System Interface Review.
February 2006 Multispectral filters flight model delivery.
February 2006 Call for Tender for Users Centers Integration
December 2005 Programming chain: the Software Specification Review was successful. The authorisation to begin the preliminary design phase was given.
December 2005 Command Control chain: the Software Specification Review was successful. The authorisation to begin the preliminary design phase was given.
December 2005 The compatibility tests between image telemetry reception stations and the on board telemetry equipment were successful.
November 2005 Users Centers Integration: The Preliminary Design Review took place. The preparation phase for the corresponding call for tender begins.
October 2005 Image chain: the Software Specification Review was successful. The authorisation to begin the preliminary design phase was given.
October 2005 Call for Tender for BPD/GIDE
October 2005 Multispectral detectors flight model delivery
June 2005 Attribution of the encrypting server for the TC link and the decipherer for the instrument TM contract to Thales-Com.
June 2005 Attribution of the Ground Segment parts supplying contracts:
    Programming chain: attributed to CAP Gemini - CSSI industrial consortium
    Image chain: attributed to Thales-IS
    Image receiving station: attributed to IN-SNEC
    Command-Control Center: attributed to CSSI
April 2005 Signature of the Agreement with Spain (Instituto Nacional de Tecnica Aerospacial).
March 2005 Signature of the Agreement with Sweden (Swedish Natioanl Space Board).
December 2004 Attribution of the launch contract to Arianespace, for a launch by a Soyouz rocket from Kourou.
September 2004 Ratification of the Turin agreement, signed in September 2001
March 2004 PLEIADES cooperation agreement signature with Sweden
December 2003 ORFEO System Definition Review
October 2003 Satellites supplying contract signature with Astrium
22-23/05/2003 "Very High Spatial Resolution Workshop at CNES
1-2/04/2003 ORFEO users' seminar
February 2003 Pleiades-HR Instrument Preliminary Definition Review
December 2002 Pleaides-HR System Design Review
28-29/05/2002 Pleaides internal seminar
April 2002 Pleaides-HR Satellite Preliminary Definition Review
March 2002 ORFEO Intermediate System Definition Review
22/06/2001 Signature of a memorandum of agreement between CNES and ASI.
At the last Paris Air Show (June 2001), a memorandum of agreement was signed between the Centre National d'Etudes Spatiales (French space agency) and the Agenzia Spaziale Italiana (Italian space agency) for the definition phase of a Dual System with an Earth observation capability using optical satellites, radar satellites and an associated ground segment.
The Dual System to be developed is composed of the following elements:
    An optical component composed of 2 satellites and the corresponding ground functions, developed under french control,
    A radar component composed of 4 satellites and the corresponding ground functions, developed under italian control,
    A user ground segment developed jointly by France and Italy
29/01/2001 Signature in Turin of a governmental agreement between France and Italy for cooperation in the field of Earth Observation.
10/05/2000 Pleaides workshop "Conceivable Systems for Pleaides"
08/03/2000 "Pleaides Requirements" users' workshop


Latest update 14/12/2009