SYNTHESIS

IASI IN ORBIT FUNCTIONAL VALIDATION


OPERATION DURATION
(DAYS)
BEGINING END    DONE COMMENTS
Beginning of the in orbit functional validation   October 24th      
Phase 1 : Switch on 1 October 24th October 24th Yes

Instrument Management Unit switch on

Phase 2 : Heater 1 mode 0 October 24th October 24th Yes

Thermal Control Unit switch on: The temperatures reach the nominal values.

Phase 3 : Decontamination 27 October 25th Novemb 20th Yes

The instrument decontamination starts on October 25th. During this phase, heaters are activated in the Cryogenic Unit for warming it at about 20 Celcius in order to avoid water vapor condensation inside the instrument.
About 7 SEU/day are detected by the Management Unit memories. The impacts are concentrated over South Atlantic and over the Poles, as foreseen. Due to the EDAC, the SEU do not affect the Management Unit functionality.
The decontamination ends on 20 of November.

Phase 4 : Cooling down 2 Novemb 20th Novemb 21th Yes

The decontamination heaters being switch off, the Cryogenic Unit cools down to - 180 Celsius.

Phase 5 : Interferometer mecanisms unlocking 2 Novemb 22th Novemb 23th Yes

The heaters of the locking device cartridges have been activated for unlocking the cube corner mecanism and the dynamic compensation mecanism.

Phase 6 : Heater 2 mode 3 Novemb 24th Novemb 26th Yes

All parameters are nominal.

Phase 7 : Initial set up 3 Novemb 27th Novemb 29th Yes

For the first time, IASI is running in Normal Operational mode. The Digital Processing Subsystem is not yet activated. The first interferograms are down loaded to the Technical Expertise Center for analysing.

Phase 8 : Operational parameters uploaded 5 Novemb 30th December 4th Yes

The Digital Processing Subsystem (DPS) parameters are issued by the Technical Expertise Center and uploaded to the instrument. The DPS is activated. The first spectra processed in board the instrument are received at the Technical Expertise Center in Toulouse. All the instrument units are working properly. The first performance analysis are promising.

Phase 9 : External calibration mode 1 Decemb 4th Decemb 4th Yes

External calibration mode is switch on. Analysis show that the radiometric performance of IASI is a little bit better than the performance measured during instrument ground testing.

Phase 10 : Routine mode 8 Decemb 4th Decemb 12th Yes

Operatioal mode is activated again.

Phase 11 : Heater 1 mode 0 Decemb 12th Decemb 12th Yes

Transition mode for going to decontamination

Phase 12 : Decontamination 6 decemb 12th decemb 18th Yes

The decontamination mode is activated for the second time for a short duration.

Phase 13 : Unlocking of the three feet       No

The necessity of unlocking the feet being not demonstrated at present time, this operation is postponed of about 3 months.

Software patch uploading 2 Decemb 18th Decemb 19th Yes

Patchs are uploaded for improving the DPS functionality and algorithms.

Phase 14 : Routine mode 20 Decemb 20th January 8th Yes

IASI is running in operational mode until the end of the functional commissioning.

End of the in orbit functional validation     January 8th Yes

Very successful functional commissioning